When Robert Sanders was sent by the Army to inspect the construction work an American company was doing on the banks of the Tigris River, 130 miles north of Baghdad, he expected to see workers drilling holes beneath the riverbed to restore a crucial set of large oil pipelines, which had been bombed during the invasion of Iraq.What he found instead that day in July 2004 looked like some gargantuan heart-bypass operation gone nightmarishly bad. A crew had bulldozed a 300-foot-long trench along a giant drill bit in their desperate attempt to yank it loose from the riverbed. A supervisor later told him that the project's crews knew that drilling the holes was not possible, but that they had been instructed by the company in charge of the project to continue anyway.
A few weeks later, after the project had burned up all of the $75.7 million allocated to it, the work came to a halt.
The project, called the Fatah pipeline crossing, had been a critical element of a $2.4 billion no-bid reconstruction contract that a Halliburton subsidiary had won from the Army in 2003. The spot where about 15 pipelines crossed the Tigris had been the main link between Iraq's rich northern oil fields and the export terminals and refineries that could generate much-needed gasoline, heating fuel and revenue for Iraqis.
For all those reasons, the project's demise would seriously damage the American-led effort to restore Iraq's oil system and enable the country to pay for its own reconstruction. Exactly what portion of Iraq's lost oil revenue can be attributed to one failed project, no matter how critical, is impossible to calculate. But the pipeline at Al Fatah has a wider significance as a metaphor for the entire $45 billion rebuilding effort in Iraq. Although the failures of that effort are routinely attributed to insurgent attacks, an examination of this project shows that troubled decision-making and execution have played equally important roles.
The Fatah project went ahead despite warnings from experts that it could not succeed because the underground terrain was shattered and unstable.
It continued chewing up astonishing amounts of cash when the predicted problems bogged the work down, with a contract that allowed crews to charge as much as $100,000 a day as they waited on standby.
The company in charge engaged in what some American officials saw as a self-serving attempt to limit communications with the government until all the money was gone.
And until Mr. Sanders went to Al Fatah, the Army Corps of Engineers, which administered the project, allowed the show to go on for months, even as individual Corps officials said they repeatedly voiced doubts about its chances of success.
The Halliburton subsidiary, KBR, formerly Kellogg Brown & Root, had commissioned a geotechnical report that warned in August 2003 that it would be courting disaster to drill without extensive underground tests.
"No driller in his right mind would have gone ahead," said Mr. Sanders, a geologist who came across the report when he arrived at the site.
KBR defended its performance on the project, and said that the information in the geotechnical report was too general to serve as a warning.
That should be the slogan for this administration ... the report was too general to serve as a warning.
It is the American people's money that this administration is pissing away daily. Why none of this is making the general public very angry is beyond me. Perhaps they are waiting for the inevitable bankruptcy that is around the corner for it to actually sink in.
Perhaps.
No comments:
Post a Comment